Dáil Éireann Debate, Tuesday - 21 February 2023

Tuesday, 21 February 2023

Questions (245)

Catherine Murphy

Question:

245. Deputy Catherine Murphy asked the Minister for Public Expenditure, National Development Plan Delivery and Reform if the refurbishment works on the new Garda office in O’Connell Street, Dublin, have been completed; if so, when the OPW will transfer this building over to An Garda Síochána. [8351/23]

View answer

Written answers

The Office of Public Works (OPW) can confirm that the works on the new Garda Station at 13A O'Connell St. Dublin will be substantially complete on 8th March 2023, handing over to An Garda Síochána thereafter.