Dáil Éireann Debate, Wednesday - 22 March 2023

Wednesday, 22 March 2023

Questions (160, 167)

Michael Ring

Question:

160. Deputy Michael Ring asked the Minister for Education to list all schools in Ireland that were granted capital funding for additional accommodation from January 2019 to date, specify in the case of each school if this funding has been reviewed/withdrawn in tabular form; and if she will make a statement on the matter. [13982/23]

View answer

Thomas Pringle

Question:

167. Deputy Thomas Pringle asked the Minister for Education if she will provide a list of all the schools on the school building programme which have recently been put on hold for all counties, including the stage at which the building project is currently at, in tabular form; and if she will make a statement on the matter. [14129/23]

View answer

Written answers

I propose to take Questions Nos. 160 and 167 together.

My Department has a strong track record of delivery of school building projects and this was achieved again in 2022 notwithstanding the wider construction sector environment of high inflation, labour shortages and supply chain issues.

Under Project Ireland 2040, we are investing €4.4 billion over the period 2021 to 2025, to add capacity and develop and upgrade school facilities across the country for the almost one million students and over 100,000 staff that learn and work in our schools every day.

My Department is very appreciative of the strong support provided by Government for our education budget. As part of the supplementary budget, €300m additional capital funding was provided in 2022. This helped to alleviate capital funding pressures that arose in 2022 which was reflective of the strong delivery by my Department of school building projects – particularly to support mainstream provision and special education needs provision. My Department’s overall capital outturn for 2022 was €1.12 billion.

The strong level of delivery is a key driver of capital pressures in the Department. In addition to the normal pressures on the school building budget, there are also additional pressures in the context of requirement to accelerate delivery of accommodation for children with Special Education Needs and also in respect of capacity for continued inflow of Ukrainian and other IP students – particularly at post-primary level where accommodation pressures are more acute

My Department's Planning and Building Unit is currently assessing its work programme and priorities for the remainder of 2023 in the context of its available funding. My Department's published NDP allocation for 2023 is €860 million. Over 70% of the NDP allocation for 2023 is needed to cover expenditure on contractual commitments on existing projects at construction carried forward from 2022. High construction inflation remains a continuing feature of the construction sector for 2023. As part of its planning ahead for the remainder of 2023, my Department is at the advanced stages of engagement with the Department of Public Expenditure, NDP Delivery and Reform in relation to capital funding pressures in order to continue to adequately support the operation of the school system with rollout of school building projects to construction in 2023. I am conscious of the numerous pressures facing the Department and their need to manage these.

I think it is best for communications to be done at individual school level and that is the approach we have taken. The Department will be providing an update to individual schools when our engagement with the Department of Public Expenditure, NDP Delivery and Reform concludes. In tandem with this, my Department’s Planning & Building Unit will also be updating Patron Bodies and School Management Bodies at that stage.

Key priorities for my Department's work programme include continuing strong delivery to support the operation of the school system with particular regard to planning ahead for the 2023/24 school year and beyond and also with particular regard to supporting special needs provision. The current status of all projects are listed on a county by county basis at www.gov.ie. and is updated on a regular basis to reflect their progress through the various stages of capital appraisal, site acquisition, design, tender and construction.