Dáil Éireann Debate, Wednesday - 20 March 2024

Wednesday, 20 March 2024

Questions (704)

Cian O'Callaghan

Question:

704. Deputy Cian O'Callaghan asked the Minister for Housing, Local Government and Heritage the time spent to carry out the four-stage approval process for publicly funded capital projects for each social housing, cost rental, affordable purchase, and mixed tenure development completed in 2022, broken down by tenure type and county, in tabular form; and if he will make a statement on the matter. [13125/24]

View answer

Written answers

Construction of new build social housing units on local authority lands follows the Capital Works Management Framework (CWMF) which includes four pre-construction stages, as follows -

• Stage 1 – Capital Appraisal

• Stage 2 – Procurement of Integrated Design Team and development outline design

• Stage 3 – Statutory Approvals including Part 8, DAC and Fire Safety, detailed design/tender documentation preparation

• Stage 4 – Tender and Contract Award

As local authorities develop each stage, they are required to provide an updated cost plan and supporting documentation so that the Department, as the funding authority, can review and confirm funding approval. These reviews are required to ensure projects achieve value for money.

An overall target programme of 59 weeks from submission of a valid Stage 1 Capital Appraisal to the award of the construction contract, was agreed with the CCMA Housing Committee and is set out in Housing Circular 2/2018. This target of 59 weeks is the expected timeline for projects of a straightforward nature. The range of local authority social housing projects includes many that are large and complex and require additional time for detailed design and statutory approvals. The 59-week target programme is broken down as follows:

-

Responsible

Target Weeks

Stage 1 – Capital Appraisal Approval, allowing LA to develop proposal

DHLGH

4

Stage 2 – Procurement of Integrated Design Team, develop outline design

Local Authority

12

Stage 2 – Approval-in-Principle

DHLGH

4

Stage 3 – Statutory Approvals include Part 8, DAC and Fire Safety, detailed design/tender documentation preparation; Public consultation can form part of this phase.

Local Authority

18

Stage 3 – Pre-tender Approval

DHLGH

4

Stage 4 – Undertake Tender

Local Authority

10

Stage 4 – Approval to Proceed (including approved budget)

DHLGH

3

Contract Award

Local Authority

4

Accordingly, the target times for both the Department and the local authorities to prepare design, achieve statutory approvals, develop tender documentation, carry out tendering, award contracts and to assess and confirm funding approval for these stages, is as follows -

Target weeks for LA Pre-construction Processes

44 weeks

Target weeks for DHLGH assessments/ approvals

15 weeks

Local authorities have options that allow them to deviate from using the above 4-stage process to achieve funding approval for social housing construction projects, depending on the size and the chosen procurement strategy for individual projects. For example, with projects below €8m and 25 homes or less, local authorities can avail of a single stage approval which takes approx. 4 weeks with the Department. In such instances, local authorities will still need to develop the design, achieve statutory approvals and run a tender programme.

Local authorities also have the option of combining Stage 2 and Stage 3 when ‘Design and Build’ projects are advanced and there is also an option to simply notify the Department if a Stage 3 proposal has been prepared by the local authority within six months of the Stage 2 approval and when the budget is at or close to the previously approved level, thus removing the requirement for the Department to provide a Stage 3 approval.

There were 69 projects completed in 2022 that used the CWMF 4-Stage Pre-construction Programme which were funded in 2021 and 2022. The times taken for these projects within the overall programme, both by DHLGH and by the local authorities, were as follows:

-

No. of Projects Approved within 15 weeks

Average Approval time by DHLGH

DHLGH Approvals

16

22

-

SHIP 4-stage (including Design & Build) Projects Completed in 2022

Average in Weeks

DHLGH time

Average Department Approvals

22

LA time

Average LA Preconstruction processes

104

DHLGH time

Stage 1 – Capital Appraisal Approval to develop proposal

6

LA time

Stage 2 – Procurement of Integrated Design Team, develop outline design, prepare Part 8 documentation

34

DHLGH time

Stage 2 – Approval-in-Principle

6

LA time

Stage 3 – Statutory Approvals including Part 8, DAC and Fire Safety, detailed design/tender documentation preparation; Public consultation can form part of this phase

41

DHLGH time

Stage 3 – Pre-tender Approval

6

LA time

Stage 4 – Tender

20

DHLGH time

Stage 4 – Approval to Proceed (including approved budget)

4

LA time

Contract Award

8

Local Authority

Total weeks to Contract Award

Total for Dept. Approvals in weeks

Total for LA Preconstruction process in weeks

All

127

21

106

Carlow

24

10

15

Cavan

157

33

124

Clare

103

22

81

Cork City

No CWMF 4-stage Project Delivered in 2022

Cork County

136

21

115

DLR

No CWMF 4-stage Project Delivered in 2022

Donegal

217

22

195

Dublin City

140

16

123

Fingal

88

16

72

Galway City

No CWMF 4-stage Project Delivered in 2022

Galway Co

122

28

95

Kerry

97

18

78

Kildare

No CWMF 4-stage Project Delivered in 2022

Kilkenny

No CWMF 4-stage Project Delivered in 2022

Laois

215

30

185

Leitrim

114

23

91

Limerick

153

33

120

Longford

No CWMF 4-stage Project Delivered in 2022

Louth

No CWMF 4-stage Project Delivered in 2022

Mayo

95

16

79

Meath

190

10

178

Monaghan

95

15

79

Offaly

124

14

111

Roscommon

No CWMF 4-stage Project Delivered in 2022

Sligo

72

21

51

South Dublin

115

22

93

Tipperary

153

32

121

Waterford

113

24

89

Westmeath

181

17

163

Wexford

128

18

110

Wicklow

88

17

71