278. Deputy Sorca Clarke asked the Minister for Education when her Department expects refurbishment works at a school (details supplied) to be completed; and the estimated cost for these works. [17407/24]

View answer

Written answers

The large scale project at the school referred to by the Deputy commenced Stage 4 Construction in September 2022.

The Project brief for the major project is an extension combined with refurbishment and upgrade works to the existing buildings to cater for 1,000 pupils.

Works are progressing on site with an expected completion date of Quarter 1 2025.