Flood Risk Management

Dáil Éireann Debate, Tuesday - 13 June 2023

Tuesday, 13 June 2023

Questions (416)

Brian Leddin

Question:

416. Deputy Brian Leddin asked the Minister for Public Expenditure, National Development Plan Delivery and Reform the costs of the ongoing maintenance and upkeep of all arterial drainage schemes over the past five years 2018, 2019, 2020, 2021 and 2022; and if he will make a statement on the matter. [27759/23]

View answer

Written answers

The Office of Public Works (OPW) is responsible for the maintenance of arterial drainage schemes completed under the Arterial Drainage Acts, 1945 and 1995, as amended. Some 2,100km of channel and some 135km of embankments are maintained annually.

The costs of the maintenance of these schemes over the past five years is detailed below :

2018

€ 16,307,648

2019

€ 17,981,876

2020

€ 18,033,466

2021

€ 17,734,703

2022

€ 19,804,228

Total

€ 89,861,921