Schools Building Projects

Dáil Éireann Debate, Tuesday - 27 June 2023

Tuesday, 27 June 2023

Questions (303)

Duncan Smith

Question:

303. Deputy Duncan Smith asked the Minister for Education if she has a plan to address the urgency for a new school building for a school (details supplied); if she will follow up her commitment to visit the school at the earliest possible convenience; and if she will make a statement on the matter. [30922/23]

View answer

Written answers

The Department of Education originally approved the construction of a standalone extension of just over 4,000m2 in area which included a two classroom Special Education needs base. Some works to the existing building were also included in this approval. Responsibility for delivering this major project for the school in question was devolved to Dublin and Dún Laoghaire Education & Training Board (DDLETB).

DDLETB experienced delays with their Design Team in finalising the detailed design process for the project as it was originally approved, and in obtaining statutory consents from the local authority. The project was brought to Stage 2B (statutory planning) of the architectural process. At that point, it was agreed to proceed with an alternative proposal for the progression of the project which involved the development of a masterplan for the demolition and replacement of the existing building but also allowed for the provision of accommodation for another school on the site.

Following receipt of DDLETB’s Design Team submission, the Department’s Professional & Technical staff are currently reviewing the options available for progressing the project. This process is nearing completion following which my Department will engage with the patron in respect of the most appropriate delivery option. As the project is at an early stage in the delivery process and in advance of any required statutory approvals, it is not possible at this time to give a date for its completion.

Pending completion of the major building project, the Department approved modular accommodation for the provision of a Home Economics Room, an Art Room, and a toilet block at the school.