Schools Building Projects

Dáil Éireann Debate, Wednesday - 17 January 2024

Wednesday, 17 January 2024

Questions (642)

Sorca Clarke

Question:

642. Deputy Sorca Clarke asked the Minister for Education when the construction works at a school (details supplied) will be completed. [1468/24]

View answer

Written answers

The project to which the Deputy refers has been devolved for delivery to Cork Education and Training Board (CETB).

The project is currently onsite (Stage 4 of the architectural process). It is envisaged that, pending no further delays or issues, the likely school occupation date will be within the first quarter of 2024. The remaining works including the demolition of the existing building, construction of the ball court, parking and associated landscaping are scheduled to be completed during quarter 2 of 2024.

My Department will continue to work closely with CETB and the Project Design Team in this regard.