185. Deputy Brendan Smith asked the Minister for Education and Skills the stage a proposed building project (details supplied) is at; when this project will proceed to the next stage; the likely timescale for this project to proceed to tender stage; and if he will make a statement on the matter. [40934/16]

Amharc ar fhreagra

Freagraí scríofa

The major building project referred to by the Deputy is at an advanced stage of architectural planning - Stage 2(b),which includes the applications for Planning Permission, Fire Certificate and Disability Access Certificate and the preparation of Tender Documents.

When the Statutory Approvals are secured the Design Team will finalise the Stage 2b (Detailed Design) submission which will be submitted to my Department by the Board of Management, as client, for review. Following receipt and consideration of that report my Department will revert to the school with regard to the further progression of the project at that time.

Barr
Roinn