155. Deputy Brendan Howlin asked the Minister for Education and Skills further to Parliamentary Question No. 96 of 24 October 2019, if a definitive date for completion of phase 1 of the project has been given; when phase two will be completed; and if he will make a statement on the matter. [52104/19]

Amharc ar fhreagra

Freagraí scríofa

The school building project to which the Deputy refers is currently on site.

The first phase, consisting of the construction of the new 8 classroom school is due for completion in Quarter 4 2019 with handover anticipated in the coming weeks. The second phase is due for completion in Quarter 2 2020.