528. Deputy Gary Gannon asked the Minister for Education the reasons for the delay in the progression of the permanent building for a school (details supplied), before and since inflationary issues have arisen. [17147/23]

Amharc ar fhreagra

Freagraí scríofa

My Department recently authorised the issue of the Letter of Acceptance to the recommended bidder for the school building project to which the Deputy refers.

Subject to no issues arising, it is envisaged that construction will commence in Quarter 2 with an estimated completion timeframe of 18 months.