Road Projects

Dáil Éireann Debate, Wednesday - 13 December 2023

Wednesday, 13 December 2023

Ceisteanna (48)

Brendan Griffin

Ceist:

48. Deputy Brendan Griffin asked the Minister for Transport the up-to-date position regarding the new M-N20 Cork to Limerick Road; if there will be a link to the N72 Mallow to Killarney Road circumventing the town of Mallow; the up-to-date timeline for the completion of the project; and if he will make a statement on the matter. [55763/23]

Amharc ar fhreagra

Freagraí scríofa

As Minister for Transport, I have responsibility for overall policy and exchequer funding in relation to the National Roads Programme. Under the Roads Acts 1993-2015 and in line with the National Development Plan (NDP), the planning, design and construction of individual national roads is a matter for Transport Infrastructure Ireland (TII), in conjunction with the local authorities concerned. This is also subject to the Public Spending Code and the necessary statutory approvals. In this context, TII is best placed to advise you on the status of this project.

I can confirm that €5,000,000 has been allocated for the M20 Limerick to Cork Road scheme in 2023. The allocations for national roads for 2024 are expected to be announced in the coming weeks.

Noting the above position, I have referred your question to TII for a direct reply. Please advise my private office if you do not receive a reply within 10 working days.