Schools Building Projects

Dáil Éireann Debate, Thursday - 9 May 2024

Thursday, 9 May 2024

Ceisteanna (175)

Aodhán Ó Ríordáin

Ceist:

175. Deputy Aodhán Ó Ríordáin asked the Minister for Education to provide a progress report on the new secondary school in Cherrywood, to include a timeframe. [21018/24]

Amharc ar fhreagra

Freagraí scríofa

The planned establishment of a new post-primary school in 2021 to serve the Sallynoggin_Killiney_DLR/Cherrywood school planning area was announced in 2018 as a result of a countrywide demographic exercise.  Further analysis has since been conducted on the necessity for the establishment of planned new schools taking into account a number of factors including the pace of delivery of the expected additional residential development in the school planning areas, associated enrolments and the capacity in existing schools in the areas.

My Department is satisfied that the existing demand can be accommodated at present by the existing and growing schools in the school planning areas. As a result, the establishment of the planned new school has been deferred.  

The pace of delivery of additional residential development in the school planning areas and particularly Cherrywood,  along with updated enrolment data and demographic data will be kept under review and this will inform the timing of school requirements. My Department will continue to liaise with the Local Authority in respect to the projected completion of planned residential developments.